In this planning year, activity on the LMS project has already begun to
trail off significantly, making time available for work that has been
mostly suspended over the last two planning years. Many goals not
fully met during this time are still here, reworded slightly to reflect
additional thinking or partial progress that was made, or are recast
within the scope of larger initiatives.
Most of the high priority work for this year falls into one of two
categories: a) coooperatively-planned LIT-wide projects, reflecting a
new trend toward collective planning in LIT, or b) improvements in Core
Services infrastructure that have been delayed.
Goals are organized below into three areas: New and improved services,
Infrastructure, and Workflow/process/organizational.
- New and improved services
- LIT on-call service.
Develop more responsive and seamless LIT
on-call service.
- Priority: HIGH
- Specifics/timeline:
- October: Convene LIT admin to review/update goals and
proposed plans.
- November-December: Implement necessary phone service;
develop
staffing schedule and automated telephone rotation; define and document
protocol for problem dispatch/notification/follow-up and tracking.
- November-December: Clarify caller responsibilities- e.g
problem
types handled, response time, reporting procedure and requirements.
- December: Rollout information to staff.
- January: Launch service.
- Institutional Repository.
Support the Institutional Repository
pilot project.
- Shibboleth.
Collaborate with ITCS to begin to offer Shibboleth
origin service for UM.
- Infrastructure
- Improvements to storage
infrastructure, web server redundancy.
Migrate storage to a networked model, then add more web servers as
needed to increase performanec under heavy load and to provide
redundancy.
- Priority: HIGH
- Specifics/timeline:
- October-December: Purchase and install first storage server
and networking hardware for central campus server room.
- January-February: Set up pilot redundant web server model
with ETS and/or HTI service.
- March: Conduct tuning and optimization.
- March: Purchase and install second storage server and
networking hardware for north campus server room.
- April-June: Migrate existing services to networked model.
- June-August: Purchase and install additional web servers as
needed.
- COSIGN. Transition
from Lib Auth to COSIGN authentication
- Priority: HIGH
- Specifics/timeline:
- November-December: Install COSIGN and pilot it with
selected
internal staff resources (involves Steinberg) that handle authorization
internally.
- January-March: Rework Lib Auth to use COSIGN authentication.
- January-March: Change local accounts to email format in
preparation for migration to COSIGN Friend accounts.
- January-March: Rework application logic as necessary to
make portable between Lib Auth and COSIGN (mostly Steinberg)
- March-April: Develop rollout plan in consultation with the
appropriate committee.
- April-May: Make final preparations for rollout and cut over.
- Positioning DLPS as a trusted
digital repository (TDR). Work
toward compliance with emerging standards for TDR best practices, using
the OAIS model as a guide.
- Specifics:
- Validation and normalization of digital objects.
Develop conventions and automation for validating and normalizing
digital objects throughout the workflow and at routine intervals to
ensure integrity.
- Support improvements in quality control. Support the
development of standards for quality control processes and develop
automated tools for doing QC work.
- Record-keeping. Support the development of standards for
record-keeping and integrate record-keeping operations into existing
automation, as appropriate.
- Persistent IDs and name resolution. Support the exploration
of
persistent identifier schemes and the implementation of one or more
schemes for DLPS-hosted material.
- Digital object and metadata encapsulation. Support the
exploration
of options for storage of digitally encapsulated objects with
their metadata.
- Disaster preparedness. Document the characteristics of our
storage environment and backup and recovery strategy.
- Redundant MySQL.
Combine production MySQL database services to
a central, dedicated, redundant pair of servers.
- Priority: HIGH
- Specifics/timeline:
- April: Purchase and install servers.
- May-June: Research, activate, and test redundancy.
- June: Develop backup procedures.
- July-August: Migrate databases to new servers.
- DHCP/DNS services.
Migrate existing DHCP services to
ITCS-provided HindSite service.
- Specifics:
- Rollout to the LIT Hatcher private network.
- Rollout to the general library networks.
- Develop an authentication and
authorization management system.
- Revisit logging practives.
Conduct a basic audit of logging
practices in LIT systems and work toward better compliance with Library
privacy policy.
- Priority: MEDIUM
- Specifics/timeline:
- December: Create inventory of systems and degree of
compliance.
- January-March: Formulate strategies for coming into
compliance.
- Ongoing: Implement strategies, where possible.
- Production server
replacements/upgrades. Increasingly
formalize the server replacement process, and work to equalize its
annual cost and improve its efficiency.
- Specifics:
- Develop updated server inventory.
- Complete pending 2003-2004 server upgrades.
- Complete migrations of unsupported RedHat versions.
- Initiate 2004-2005 server upgrades.
- Formalize system administration
infrastructure.
- Define and document the characteristics of the standard
environment: what platforms and operating systems are supported, what
software packages are installed, which of those are centrally
administered, etc.
- Explore tools and brainstorm models for centralized system
administration.
- Set up system administration resources such as servers,
software, etc. as necessary.
- Begin transition of servers to centralized model.
- Replace DLXS statistics.
Research off-the-shelf solutions to
replace the existing usage statistics system to facilitate operation by
collection management staff and release of the system via DLXS.
- Centralize LIT backup.
Migrate departmental CS and DSS backup
services
to a larger-scale, centralized backup infrastructure, purchasing or
re-using equipment as appropriate, to reduce costs and improve scale.
- Priority: MEDIUM
- Specifics:
- Convene CS and DSS staff to discuss priorities, software
options, staffing impact, and other ideas.
- Identify tools and existing resources from which to build a
centralized system.
- Begin to build the system and transition servers.
- Development server
replacements/upgrades. Conduct
periodic assessments of development servers and identify areas of need.
With input from users, consider a) consolidating services, b)
repurposing
retired production servers (if still viable), and/or c) purchasing new
equipment or upgrades as appropriate. Work to achieve a balance between
a robust environment and management overhead.
- Security assessment.
Conduct an assessment of security
practices, document them, and make improvements where necessary.
- Workflow, processes, and organizational work
- LIT work requests and
scheduling. Improve communication of work
requests across LIT, including scheduling.
- Priority: HIGH
- Specifics/timeline:
- October-November: Research options and make a selection
- December-January: Install and configure the system and
develop a basic familiarity with the capability and features
- January-February: Discuss, within LIT admin, the scope of
use, common conventions, and training/orientation needs
- March-April: Migrate management of work queue to system
- Clearly articulate LIT
services and resources. Develop clear
communication methods and products about the many roles of LIT
departments within the Library.
- Specifics/timeline:
- October-November: Develop updated Overview of Services
&
Activities documents for each LIT unit based on those developed in 2000
for the LITPTF.
- November: Deliver these documents via the web with
publicity in
Library Newsletter and LIT managers volunteer departmental meetings.
- January: Reestablish regular Library Technology Updates to
be held on a quarterly basis.
- January: LIT Managers volunteer to begin to schedule
departmental meetings to describe/promote LIT services and activities.
- November: Improve representation of internally-focused LIT
units on Staff website.
- November: Improve representation of DLPS collections and
services to external clients on Library’s gateway site.
- Documentation and
standardization of processes. Organize
and
fill gaps in documentation of the current environment and normal
operations; use the process of documenting processes as an opportunity
to develop and implement stanadards for those processes.
- Specifics:
- Develop a comprehensive list of items that need
documentation and processes that need checklists, organize this list
into a hierarchy, and assign responsibility for sections.
- Devote time each month to writing sections of documentation
according to priority.
- Improve coordination of data
loading. Establish communications
as appropriate to better coordinate demand for data loading.
- Cost model. Continue
development of the model for core
service costs based on a simple, known variable such as page or image
count, to better quantify resources needed in Core Services.
- Technology trends awareness.
Pursue a modest number of
options such as trade magazine subscriptions or technology conferences
to stay abreast of development in relevant technologies.